script 1 :-

declare @job_ids sysname
declare @schedule_ids sysname
declare @str varchar(4000)
declare @env varchar (1000)
set @env ='%china_jobs%'------------------------------------------------Mention common filter in all jobs here
declare @date varchar (500)
set @date ='20180412'--------------------------------------------------Mention date in YYYYMMDD format


declare  job_enable_cursor cursor for
select jn.job_id,js.schedule_id from sysjobs jn join sysjobschedules js on jn.job_id=js.job_id
where jn.name like @env and jn.enabled = 1

OPEN job_enable_cursor

FETCH NEXT FROM job_enable_cursor  
INTO @job_ids, @schedule_ids 
WHILE @@FETCH_STATUS = 0

begin

select @str = 'EXEC msdb.dbo.sp_attach_schedule @job_id=N'''+ @job_ids +''',@schedule_id='+@schedule_ids+
' EXEC msdb.dbo.sp_update_schedule @schedule_id='+@schedule_ids+', @enabled=1,@active_end_date='+@date

exec (@str)

FETCH NEXT FROM job_enable_cursor  
INTO @job_ids, @schedule_ids 


end
close job_enable_cursor
deallocate job_enable_cursor

go



Script 2 :-




declare @job_ids sysname
declare @schedule_ids sysname
declare @str varchar(4000)
declare @date varchar (500)
set @date ='20180412' -------------------------- Mention date in YYYYMMDD format

declare  job_enable_cursor cursor for
select jn.job_id,js.schedule_id from sysjobs jn join sysjobschedules js on jn.job_id=js.job_id
Where  jn.enabled = 1 and

 jn.name in  ('Job_1','Job_2')-----------------------------mention job names here



OPEN job_enable_cursor

FETCH NEXT FROM job_enable_cursor  
INTO @job_ids, @schedule_ids 
WHILE @@FETCH_STATUS = 0

begin

select @str = 'EXEC msdb.dbo.sp_attach_schedule @job_id=N'''+ @job_ids +''',@schedule_id='+@schedule_ids+
' EXEC msdb.dbo.sp_update_schedule @schedule_id='+@schedule_ids+', @enabled=1,@active_end_date=@date

exec (@str)

FETCH NEXT FROM job_enable_cursor  
INTO @job_ids, @schedule_ids 


end
close job_enable_cursor
deallocate job_enable_cursor

go